Drivers hoping to make use of Saskatoon’s College Bridge should wait longer, as town as soon as once more pushes again its reopening date to most of the people because of development delays.
The bridge will stay closed “close to time period” to non-emergency autos as close by School Drive development and bridge rehabilitation work continues, town stated in a Friday information launch.
At present, solely emergency autos are allowed to make use of the bridge whereas development continues, one thing town stated stays a “prime precedence.”
Saskatoon closed the College Bridge on April 6 for repairs, initially planning to reopen it in June. That timeline was later pushed to mid- to late July due to weather-related development delays, based on town.
Town has revised its opening plan after exploring “a number of choices,” stated Terry Schmidt, Saskatoon’s transportation and development supervisor, in an announcement to International Information.
Beforehand, the bridge was imagined to open to single-lane, two-way site visitors. However now town is ready for 3 site visitors lanes to change into out there so one lane might be devoted to emergency autos, stated Schmidt.

Get breaking Nationwide information
Get breaking Canada information delivered to your inbox because it occurs so you will not miss a trending story.
Schmidt stated this choice got here after additional overview and discussions with emergency providers and the Saskatchewan Well being Authority (SHA).
“Nobody needs to create a situation the place an ambulance, hearth truck, or police automobile is trapped in site visitors,” Schmidt stated in an announcement.
The Saskatchewan Most cancers Company stated in an announcement to International Information that its shuttle has permission to make use of the bridge throughout the closure and recommends sufferers plan their journeys accordingly.
The SHA stated it has been collaborating with the town and different stakeholders throughout the development to make sure emergency autos have entry to its amenities.
“The SHA helps the well timed resumption of normal site visitors throughout the bridge and alongside School Avenue Drive as quickly as it’s protected to take action, and is working with town to take care of entry for emergency autos, whereas additionally sustaining affordable different entry for all medical providers it’s protected to take action,” the well being authority stated in an announcement to International Information.
Town has not supplied a brand new reopening date.
Extra repairs improve challenge prices
Town can be rising the price range for the College Bridge archway rehabilitation challenge after discovering extra in depth deterioration throughout an inspection.
Town says crews found “better than anticipated concrete loss” via an inspection when a brief work platform was put in in early June.
“The choice was made to proceed with these repairs to benefit from having the short-term work platform already in place and keep away from needing to return to finish these needed repairs inside a number of years,” town instructed International Information in an announcement.
These further repairs are anticipated to extend the challenge’s value by $213,000. The price for the rehabilitation challenge was initially $1.5 million.
Whereas town can’t present a date for the bridge’s reopening, its web site now says it expects archway repairs to be accomplished by mid- to late September. It stays unclear whether or not normal site visitors shall be allowed again onto the bridge earlier than rehabilitation work is full.